As of this date, February 27, 2014, we are deep into the renovation of our fix-r-upper home we purchased in December 2013. With some unfortunate delays, our approximate move-in date is now mid-April. The renovation has gone fairly well but more projects and planning than I had anticipated. Greg is doing an incredible job but I think, he too, would admit more was involved than originally thought. It will be a beautiful home when finished. The view is just spectacular!! Also, Greg has retired "take two" as of January 2014. Hooray!! Here's the timeline for the completion of our home:
Tuesday, February 26 - Kitchen appliances were delivered
Wednesday, February 27 and 28 - Electrical and plumbing for master and guest baths/rough in
Monday, March 3 - Electrician starts in kitchen
Monday, March 10 - Lighting in master and guest baths
Wednesday, March 12 - 14 - Kitchen cabinets and applicances installed
Monday, March 17 - sinks and faucets installed in master and guest baths
Thursday, March 20 - Granite kitchen countertop measure/install 10 days later
Monday, March 24 - 25 - Carpet installed
Week of April 1 - Hopefully, move in
Thursday, February 27, 2014
Thursday, January 30, 2014
Our 12th grandchild is born.......
On January 30th, our 12th grandchild, a grandson, Kasen Jacob was born to Jake and Jackie. We are so very happy to welcome Kasen to our family. Kasen is now 3 years old and loves being a Super Hero. Never know who he will be, Batman, Superman, Spider-Man......Definetly a little boy Super Hero in disquise.
Saturday, January 18, 2014
Our 11th grandchid is born......
On January 18th, our 11th grandchild, a granddaughter, Justene Marie was born to Joel and Joyce. We are so very happy to welcome Justene to our family.
Subscribe to:
Posts (Atom)